The Effect of Risk Management Practices on Project Performance: A Case Study of the Libyan Construction Industry

Authors

DOI:

https://doi.org/10.26668/businessreview/2023.v8i6.1420

Keywords:

Risk Management, Construction Industry, Project Management, Smart-PLS

Abstract

Purpose: The general aim of the study was to investigate the implementation of risk management in the construction industry in Libya.

 

Theoretical framework: The role of risk management in project management in the construction industry in Libya is described in this paper. The study involved more than three hundred construction companies located in Tripoli and Benghazi as these are two main cities in Libya where construction was most active and involved big projects and large investment.

 

Design/methodology/approach: Questionnaires which were designed based on cluster sampling were sent to respondents i.e., basically the company managers and 250 replies were obtained. Structured equation modelling was used to analysis the information by Smart-PLS program. The risk management processes defined by identification, assessment and monitoring which contributed to the project success was also related to the financial risk.

 

Findings: The study found that risk management practices had substantial and favourable effects on the success of the project's execution. Further the awareness of quality management in terms of risks was most encouraging.

 

Research, Practical & Social implications: The current findings of this research have shown that   most studies focus on the effect of risk management practices as strong tool to improve the project performance.  A productivity  survey  might  give  a better overview of risk management at other sectors as it concerns the actual output of the construction companies.

 

Originality/value: The systematic literature review approach was hardly found in study of risk management and project performance. At the same time, the exploratory method was applied to synthesize previous studies on risk management and project performance in construction companies.

Downloads

Download data is not yet available.

References

Alfakhri, A., Ismail, A., Muhamad, A. K., Arhad, I., & Irtema, H. (2017). A conceptual model of delay factors affecting road construction projects in Libya. Journal of Engineering Science and Technology, 12(12), 3286–3298.

Ali, M. M., Norman, S. Z., Ghani, E. K., & Haron, N. H. (2018). The influence of risk management on construction project performance: a case study. The Journal of Social Sciences Research, 936–942.

Amoah, C., & Pretorius, L. (2019). Evaluation of the impact of risk management on project performance in small construction firms in South Africa: The case study of construction systems. Journal of Engineering, Design and Technology.

Banaitiene, N., & Banaitis, A. (2012). Risk management in construction projects. Risk Management–Current Issues and Challenges. In N. Banaitiene (Ed.), Risk Management–Current Issues and Challenges, 429–448.

Boateng, A., Ameyaw, C., & Mensah, S. (2020). Assessment of systematic risk management practices on building construction projects in Ghana. International Journal of Construction Management, 1–10.

Chen, J., De Cesari, A., Hill, P., & Ozkan, N. (2018). Initial compensation contracts for new executives and financial distress risk: An empirical investigation of UK firms. Journal of Corporate Finance, 48, 292–313. https://doi.org/10.1016/j.jcorpfin.2017.11.002

Chilumo, J., Odiembo, S., Aloo, Z., Ruwa, A. H., Mwakwi, S., Kithome, O. M., & Kyalo, D. N. (2020). Risk Management Practices on Performance of Building Construction Projects. Journal of Entrepreneurship & Project Management, 4(6), 38–57.

Alfakhri, A., Ismail, A., Muhamad, A. K., Arhad, I., & Irtema, H. (2017). A conceptual model of delay factors affecting road construction projects in Libya. Journal of Engineering Science and Technology, 12(12), 3286–3298.

Ali, M. M., Norman, S. Z., Ghani, E. K., & Haron, N. H. (2018). The influence of risk management on construction project performance: a case study. The Journal of Social Sciences Research, 936–942.

Amoah, C., & Pretorius, L. (2019). Evaluation of the impact of risk management on project performance in small construction firms in South Africa: The case study of construction systems. Journal of Engineering, Design and Technology.

Banaitiene, N., & Banaitis, A. (2012). Risk management in construction projects. Risk Management–Current Issues and Challenges. In N. Banaitiene (Ed.), Risk Management–Current Issues and Challenges, 429–448.

Boateng, A., Ameyaw, C., & Mensah, S. (2020). Assessment of systematic risk management practices on building construction projects in Ghana. International Journal of Construction Management, 1–10.

Chen, J., De Cesari, A., Hill, P., & Ozkan, N. (2018). Initial compensation contracts for new executives and financial distress risk: An empirical investigation of UK firms. Journal of Corporate Finance, 48, 292–313. https://doi.org/10.1016/j.jcorpfin.2017.11.002

Chilumo, J., Odiembo, S., Aloo, Z., Ruwa, A. H., Mwakwi, S., Kithome, O. M., & Kyalo, D. N. (2020). Risk Management Practices on Performance of Building Construction Projects. Journal of Entrepreneurship & Project Management, 4(6), 38–57.

Dakhil, A. (2013). The contribution of the construction industry to economic development in Libya. Liverpool John Moores University.

Ekung, S., Lashinde, A., & Adu, E. (2021). Critical Risks to Construction Cost Estimation. Journal of Engineering, Project & Production Management, 11(1).

Falk, R. F., & Miller, N. B. (1992). A primer for soft modeling. University of Akron Press.

FERNANDES, V. (2012). (Re) discovering the PLS approach in management science. M@ N@ Gement, 15(1).

Fisher, P., & Robson, S. (2006). The perception and management of risk in UK office property development. Journal of Property Research, 23(2), 135–161.

Gyamfi, T. A., Pratt, L., & Nana-Addy, E. (2018). Assessing the Effect of Risk on Public and Private Construction Projects Performance in Ghana: Consultant Perspective.

Hair, J. F., Risher, J. J., Sarstedt, M., & Ringle, C. M. (2019). When to use and how to report the results of PLS-SEM. European Business Review.

Hair, J., Hult, G. T. M., Ringle, C., & Sarstedt, M. (2014). A Primer on Partial Least Squares Structural Equation Modeling.

Harvett, C. M. (2013). A study of uncertainty and risk management practice relative to perceived project complexity. Bond University, Australia.

Hasani, A., & Abdullah, M. M. (2019). An investigation into risk management practices in construction projects : the case of United Arab Emirates . An Investigation into Risk Management Practices in Construction Projects : The case of United Arab Emirates Mundhir Mahmood Abdullah AL-Hasani.

Higham, A. P., & Troug, M. A. (2018). Exploration of time delay and cost overrun in Libyan public housing projects. University of Salford. http://usir.salford.ac.uk/48625/%0Ahttps://www.emeraldinsight.com/doi/10.1108/BEPAM-10-2017-0088

Ismail, A., Y. Y. Alfakhri, A., Azry Khoiry, M., M Abdelsalam, H., & Elhub, B. (2018). Investigating Delays in Libyan Road Construction Projects Using Structural Equation Modelling (SEM). International Journal of Engineering & Technology, 7(2.29), 858. https://doi.org/10.14419/ijet.v7i2.29.14272

Liu, J., Zhao, X., & Yan, P. (2016). Risk paths in international construction projects: Case study from Chinese contractors. Journal of Construction Engineering and Management, 142(6), 5016002.

Marinich, M. (2020). Relationship between Risk Identification, Risk Response, and Project Success. Walden University.

Masengesho, E., Wei, J., Umubyeyi, N., & Niyirora, R. (2020). A Review on the Role of Risk Management (RM) and Value Engineering (VE) Tools for Project Successful Delivery. World Journal of Engineering and Technology, 9(1), 109–127.

Nguyen, L. H., & Watanabe, T. (2017). The impact of project organizational culture on the performance of construction projects. Sustainability, 9(5), 781.

Obondi, K. C. (2020). The impact of project risk audits on construction project success. Journal of Engineering Management and Competitiveness (JEMC), 10(2), 103–115.

Pirwani, W., Asim, M., & Manzoor, M. S. (2020). Analysis of Vulnerability Rates in Construction Projects due to Lack of Risk Management in Pakistan.

Shakatreh, M., Rumman, M. A. A., & Mugableh, M. I. (2023). Reviewing the Framework of Risk Management: Policy and Hedging. International Journal of Professional Business Review, 8(1), e0928. https://doi.org/10.26668/businessreview/2023.v8i1.928

Renault, B., Agumba, J., & Ansary, N. (2018). An exploratory factor analysis of risk management practices: A study among small and medium contractors in Gauteng. Acta Structilia, 25(1), 1–39.

Rostami, A., & Oduoza, C. F. (2017). Key risks in construction projects in Italy: contractors’ perspective. Engineering, Construction and Architectural Management.

Sabiel, I. A. (2020). The Role of Formal Risk Management Practices in Construction Projects’ Success: A Case Study of Qatar. Capella University.

Sarstedt, M., Ringle, C. M., & Hair, J. F. (2017). Treating unobserved heterogeneity in PLS-SEM: A multi-method approach. In Partial least squares path modeling (pp. 197–217). Springer.

Sarstedt, M., Ringle, C. M., Smith, D., Reams, R., & Hair Jr, J. F. (2014). Partial least squares structural equation modeling (PLS-SEM): A useful tool for family business researchers. Journal of Family Business Strategy, 5(1), 105–115.

Shibani, A., & Gherbal, N. (2018). Using the balanced scorecard as a strategic management system in the Libyan construction industry. Management Studies, 6(1), 1–19.

Tahir, H. A. (2015). A project control framework for the Libyan construction industry. Sheffield Hallam University,.

Tahir, O., Tahir, I., & Shujaat, S. (2019). Effects of Risk Management Practices on Project Success in the Construction Industry of Pakistan. International Journal of Business and Management Study–IJBMS, 6(2).

Ranganathan, P., & Sujatha, S. (2022). Occupational Accidents and Need for Worker Safety in Manufacturing and High Risk Industries – An Explorative Study With Solutions. International Journal of Professional Business Review, 7(6), e0670. https://doi.org/10.26668/businessreview/2022.v7i6.e670

Unterhitzenberger, C., & Bryde, D. J. (2019). Organizational justice, project performance, and the mediating effects of key success factors. Project Management Journal, 50(1), 57–70.

Urbach, N., & Ahlemann, F. (2010). Structural equation modeling in information systems research using partial least squares. Journal of Information Technology Theory and Application, 11(2), 5–40.

Urbański, M., Haque, A. U., & Oino, I. (2019). The moderating role of risk management in project planning and project success: Evidence from construction businesses of Pakistan and the UK. Engineering Management in Production and Services, 11(1), 23–35. https://doi.org/10.2478/emj-2019-0002

World Bank. Accessed 10 Sept (2015) Available from: https://www.albankaldawli.org/ar/country/libya

Downloads

Published

2023-06-29

How to Cite

Nasreddine Ali Algremazy, Ideris, Z., Alferjany, M. A., & Akram, A. (2023). The Effect of Risk Management Practices on Project Performance: A Case Study of the Libyan Construction Industry. International Journal of Professional Business Review, 8(6), e01420. https://doi.org/10.26668/businessreview/2023.v8i6.1420